Day 1: The work begins Burying new service entrance cables New service entrance at the building Placing the new transformer Lots of wires! New Transformer complete Removing old transformer Digging up the yard! This cabinet caused 3 month delay = supply chain issues Everything is new! new pedestal for heat pumps 3 – 5 ton heat pumps new mini-split in annex removing the old ductwork ductwork nearly all gone ductwork gone! new VRF lines ceiling mounted head unit VRF manifold reinstalling ceiling tile heat pump head units in Sanctuary digging out the old fuel oil barrel fuel oil barrel – 5.5’x13′, 2,000 gallons! excavating French drain a big hole! excavation complete! 200 ton of crush rock compacted every 5″ of depth! new sidewalks removing rooftop furnaces they were big! and ugly! the last one! it’s pergola time! pounding pegs…no nails or screws! 4 hours, 4 guys and a crane! it takes a monkey! pergola complete! permeable pavers courtyard paving begins Kyle doing great work! close to done! couryard complete! the original “Good Shepherd cross!” the tarp was for shading solar racking rafters assembling rafters lifting rafters onto pergola solar panel install solar install volunteer crew 3 different solar arrays total 55 kW of power! time to make electricity! looking to the south LED strip lighting restoring the yard hydroseeding complete Grass! Wood screen covering electrical panels